Skip to content
[ 05 ]Journal

Towns Have Blocked $130 Billion of AI Data Centers. The Bottleneck Was Never the Chips.

Local resistance has blocked or delayed roughly $130B of AI data centers. The constraint on AI is now the grid and the zoning board, and it changes the math for everyone building on inference.

Towns Have Blocked $130 Billion of AI Data Centers. The Bottleneck Was Never the Chips.
Listen to this · AI voice8 min

By , Founder & CEOPublished

For three years the AI infrastructure story was a story about GPUs. Who had them, who was waiting for them, how many a hyperscaler had on order. Allocation was the moat, and the companies that secured supply early were treated as if they had secured the future.

That framing is now out of date. The constraint that decides where AI gets built in 2026 is not silicon. It is the electrical interconnect, and increasingly, the county zoning board.

Data Center Watch, which tracks local opposition, counted at least 75 projects worth roughly $130 billion blocked or delayed by local resistance in the first quarter of this year alone, the most in any three months since it began tracking in 2023 and roughly equal to all of 2025. The second quarter added about 45 more projects worth $68 billion. The tracker does not publicly separate projects killed outright from projects stalled, so the honest reading is "blocked or delayed." That is still capital that had chips, land, and financing lined up and did not get built on schedule, because the community on the other side of the fence decided the trade was not worth it.

Why the town hall turned

The pushback is not irrational, and founders who dismiss it as NIMBYism are misreading the room.

PJM Interconnection, the grid operator serving about 67 million people across thirteen states and Washington, D.C., runs an auction that sets what utilities pay to guarantee future capacity. That price was $28.92 per megawatt-day for the 2024/25 delivery year. It jumped to $269.92 in the auction held in mid-2024 and reached $333.44, the FERC-approved cap, in the December 2025 auction. The July 2026 auction cleared at its own cap of $325 and still fell 6,831 MW short of PJM's reliability requirement; PJM estimates the uncapped price would have been $554.72. Those costs flow into retail bills. PJM's independent market monitor estimates data centers have cost the region's ratepayers about $29 billion over roughly two years.

Nationally, Goldman Sachs says electricity prices rose nearly 7% in 2025, more than double headline inflation of 2.9%, and expects household bills to keep climbing through 2027. Bloomberg's analysis of wholesale prices found costs at some grid nodes near data center clusters up as much as 267% over five years. That is a wholesale figure, and as PolitiFact has pointed out, it is not the same as a 267% rise in household bills.

The evidence is genuinely contested. An EPRI working paper found data centers actually lowered average retail rates from 2015 through 2024 by spreading fixed grid costs across more load. A study by E3, commissioned by the Data Center Coalition, found no historical evidence that data centers are driving residential increases under existing rate structures. Both can be true: the effect is real in constrained regions like PJM and overstated in regions with spare capacity. Both studies also look backward, and the PJM auctions above show the forward-looking price is a different number.

But voters do not experience national averages. They experience their own bill, a new substation on the road they drive, and a facility that employs a few dozen people after construction. As NPR reported last week, there is no universal answer to how much of a grid upgrade serves a data center and how much serves everyone else, and in practice the costs are spread across every meter in the region. That is a political problem, and political problems get solved at the ballot box in November.

The shortfall is structural

Morgan Stanley's latest estimate, published October 5, puts the net U.S. data center power shortfall through 2028 at about 32 gigawatts, roughly a third of the additional power planned facilities need, even after counting on-site generation and fuel cells. Earlier estimates from the same bank ran higher. For scale, a gigawatt is roughly a large nuclear reactor. You cannot procure your way out of a gap that size with a purchase order. New transmission lines routinely take the better part of a decade to permit and build. Gas turbines are back-ordered. Small modular reactors are a 2030s story.

This connects directly to the capex argument we made in $725 Billion of AI Capex This Year. Capital is not the scarce input anymore. Power is. And unlike capital, power cannot be raised in a quarter.

What this means if you are not a hyperscaler

Most of the founders we work with will never site a data center. They should still care, because the power constraint shows up in their business in three places.

Inference prices stop falling as fast. The assumption baked into most AI product plans is that the cost per token falls roughly an order of magnitude every year or two. Some of that comes from better models and chips, which continue. But if the marginal megawatt gets more expensive and harder to find, the floor under inference pricing rises. Plan for costs that decline, but more slowly than the last three years taught you to expect.

Capacity becomes regional and allocated. When capacity is tight, providers prioritize large committed customers. If your product depends on low-latency inference in a specific region, or on bursty capacity at peak, assume you will be the first customer throttled. Build for graceful degradation and keep a second provider wired in.

Efficiency becomes a feature again. For a while, the dominant strategy was to throw the largest model at every problem and let falling prices bail you out. That stops working when prices plateau. The teams that route easy work to small models, cache aggressively, and measure tokens per outcome will have a margin advantage that compounds.

The opportunity hiding in the constraint

Every hard constraint creates a market around it, and this one is unusually large.

  • Grid software. Interconnection queues are still largely managed with spreadsheets and PDFs. Tooling that shortens the study process by even a few months is worth a great deal to anyone waiting in line.
  • Flexible load. A data center that can curtail during peak hours is far easier to permit. Orchestration that makes AI workloads interruptible, moving training and batch jobs to off-peak windows, turns a liability into an asset for the grid operator.
  • Community economics. The projects that get approved will be the ones that bring something to the town: tax structure, local jobs, paid-for grid upgrades, heat reuse. There is room for companies that structure and verify those commitments.
  • On-site generation and storage. Behind-the-meter power is moving from niche to default for new builds, and the financing and operations layer around it is immature.

The honest version

The AI buildout is not going to stop. Demand is real, and the money is already committed. But the era where the only question was "can you get chips?" is over. The next era will be decided by people who understand utilities, permitting, and local politics, which is to say the least glamorous parts of the stack.

The companies that win it will not look like AI companies. They will look like infrastructure companies that happen to serve AI. That has historically been a very good business to be in.

Sources